Renovation, Modernisation, Uprating & Life Extension
Serial No. | Name of Power Station | Capacity (in MW) | Status |
---|---|---|---|
1. | Chilla HEP | 4 X 36 |
1. Pre RMU activities e.g. Reverse Engineering, Model Testing and major items design activities etc are completed. 2. 1st Machine handed over to M/s BHEL on 07/11/2024 for RMU Works and scheduled to be completed by 31/12/2025. 3. Overall completion of RMU works is scheduled on 31/10/2027. |
2. | Dhakrani HEP | 3 X 11.25 |
1. RMU works of 1 Machine completed on 01/03/2025. 2. RMU of 2nd Machine started w.e.f. 16/03/2025 and scheduled to be completed by 15/10/2025. 3. Overall completion of RMU works is scheduled on 31/05/2026. |
3. | Dhalipur HEP | 3 X 17 |
RMU works of Dhalipur HEP is completed on 07.10.2023 |
4. | Khatima Power Station | 3 X 13.8 |
RMU Works (Electro-mechanical & Hydro-Mechanical) Completed on 08.09.2016 |
5. | Kulhal HEP | 3 X 10 |
1. In line to the directives of Hon’ble APTEL vide order dated 04/09/2024, fresh DPR of Rs. 120.g9 Cr. (including IDC) based on the current requirements of RMU works was prepared and got approved in 123 BOD. 2. Petition of investment approval for RMU works has been filed before Hon’ble UERC on 30/12/2024 and is under observation. |
6. | Mohammadpur Power Station | 3 X 3.1 | RMU work of Mohammadpur Power Station is completed on 21/07/2013 |
7. | Pathri Power Station | 3 X 6.8 | RMU works completed on 30/11/2014 |
8. | Tiloth HEP (MB-1) | 3 X 30 | RMU works of Tiloth HEP is completed on 08.09.2022 |
9. | Ramganga HEP | 3 X 66 | In line to the directives of Hon’ble APTEL vide order dated 04/09/2024, preparation of fresh DPR based on the current requirements of RMU works is under progress. |